Habitat House Build #114
530 Haynes Street
Clute, TX
March 17, 2022
To all HfH volunteers,
The slab is now ready for our next Habitat home build scheduled to start Thursday, March 17, 2022, located at 530 Haynes Street in Clute. This will be the 1st house built this year and the 1141h Habitat house built in our local area since 1991.
Ctrl + Click on the following link to display a map to the build site.
A tentative schedule of the work planned for each day is at the end of this e-mail. Note, the most work for volunteers is during the first 5-6 days of the build, especially on week days. Towards the end of the build, much of the work is done by contractors. That work is denoted in red and volunteers will not be needed for that work.
Build Information:
Sign-in, devotional, and breakfast are 7:30 to 8:00 a.m. each day at the big hospitality tent at the site. Work starts about 8:00 a.m. and runs until about 4:00 p.m. However, you can come and go at any time. Breakfast, lunch, water, lemonade and snacks will be provided during the regular work days except as noted in the build schedule at the end of this email.
Any and all volunteers of any skill level are welcome to participate on any of the work days. There will be skill leaders present to direct the work and to show anyone how to do an unfamiliar job. Most tools will be provided. However, you might want to bring your own hammer, tape and/or tool belt if you have them. So, find a job you want to do or take advantage of on-the-job training, and come help. Please note that there are age restrictions for safety reasons as follows:
- No one under 16 can be on an active construction site.
- No one under 18 is allowed to do any hazardous activities such as the use of power tools, roofing or working from a height of 6′ or more.
- Those 14-15 can do painting when there is no active construction work going on at the site, but should be supervised by an adult.
- Volunteers under 16 years old can help with landscape work if accompanied by an adult.
- All volunteers must have a signed waiver to work. Waivers for minors must be signed by parents/guardians and notarized.
If you have not done so in the last year, adults will also need to complete a waiver before your first day of work. All this can be done before you volunteer using the attached document or on the first day you volunteer.
Hope to see you at the build.
Jim Erskine
Habitat for Humanity Volunteer Coordinator
PRE-BUILD SCHEDULE
Thursday 3/10 – No Meal
Delivery of materials for prefab items (door & window frames, corners & tees).
Build porch & carport beams, door & window frames, corners & tees.
Cut and mark plates.
Friday 3/11 – No Meal
Finish marking plates, beams, and precuts.
Wednesday 3/16 – No Meal
Take delivery of studs, lumber, tub and shower
Set hospitality tent if not done earlier
MAIN BUILD SCHEDULE
Thursday 3/17 (Day 1) – Meal
Build and erect walls
Set porch beams (& carport beam, if needed) and posts.
Friday 3/18 (Day 2) – Meal
Finish building walls
Square walls and brace walls
Set roof joists
Start outside wall sheathing
Saturday 3/19 (Day 3) – Meal
Take delivery of windows and ext. doors
Install ext. doors
Install rafters & jack rafters
Install roof bracing
Set front porch gable
Install porch lookouts, fascia, purlins etc.
Monday 3/21 (Day 4) – Meal
Install blue board on outside walls
Prepare window openings and install windows and trim boards
Install inside deadwood for drywall and attic stairs
Start roof decking
Tuesday 3/22 (Day 5) – Meal
Continue roof decking
Start electrical installation
Start vinyl siding.
Continue window installation if not already finished.
Wednesday 3/23 (Day 6) – Meal
Continue roof decking.
Install roof tar paper.
Take delivery of Sheetrock & insulation.
Put Sheetrock in house (needs to be done before trustees leave).
Continue electrical work.
Take delivery of shingles. (shingling donated by Galaxy Roofing)
Vinyl siding continued.
Thursday 3/24 (Day 7) – Meal
Finish roof decking.
Finish rough electrical work (if not already completed). A day to do the finish electrical work will be announced later.
Install baffles over soffit.
Continue vinyl siding.
Friday 3/25 (Day 8) – No meal
Start AC installation (by contractor)
Install insulation under attic decking.
Install gas line (by contractor)
Start shingling (labor donated by Galaxy Roofing)
Saturday 3/26
No work.
Sunday 3/27
No work.
Monday 3/28 (Day 9) – No Meal
Rough plumbing (by contractor)
Tuesday 3/29 (Day 10) – No Meal
Wall insulation by Contractor
Wednesday 3/30 (Day 11) – No meal
Inspection – electrical, plumbing and mechanical (heating, ventilation & air conditioning-HVAC) rough-in Inspection by city & insulation inspection for Energy Star
Thursday 3/31 (Day 12) – No meal
Start hanging Sheetrock (by contractor)
Friday 4/1 (Day 13) – No meal
Tape and mud Sheetrock (by contractor)
Saturday 4/2
No work.
Sunday 4/3
No work.
Monday 4/4 (Day 14) – No meal
Texture Sheetrock (by contractor)
Tuesday 4/5 (Day 15) – No meal
Tentative date for preparing the house for interior painting. Another email will be sent out before this date, when the build progress can be better assessed. This work consists of the completion of caulking and covering of nail holes (if not completed on Friday), sweeping floors and covering them with brown paper, covering windows with brown paper & plastic, covering bathtub & shower and taping door hinges. Four to six people are needed for four to six hours. It also includes delivering the primer, paint, paint sprayer and all other needed tools and supplies to the jobsite (house).
Wednesday 4/6 (Day 16) – No meal
Interior painting (by contractor)
Thursday 4/7 (Day 17) – No meal
Flooring (by contractor)
Friday 4/8 (Day 18) – No Meal
Cabinets – Four to six volunteers are needed for four to six hours
Saturday 4/9 (Day 19) – No Meal
Final Trim
Monday 4/11(Day 20)
FORMICA in kitchen & bathroom lavatories (by contractor)
Tuesday 4/12 (Day 21)
Finish electrical work. Tentative. Electrical team will be notified when exact date can be determined.
Wednesday 4/13 (Day 22)
Final plumbing (by contractor)
Utility Service Inspection for electricity & gas connection (by city)
Thursday 4/14 (Day 23)
Set air conditioner condenser and install trim for central A/C & heat (by contractor)
Friday 4/15
No Work
Saturday 4/16 (Day 24)
Tentative landscaping day (this is work youth and family groups can do). Another email will be sent out before this date, when the build progress and weather can be better assessed and this date can be confirmed or a new date set.
Monday 4/18 (Day 25)
Commission A/C and heat (by contractor)
Tuesday 4/19 (Day 26)
Blown insulation in attic (by contractor)
Wednesday 4/20 (Day 27)
Certificate of Occupancy inspection by city
Energy Star Final Inspection including door blower test & duct leakage test (by contractor)